Government has introduced a Games-specific approvals framework that changes how cultural heritage is managed for certain Games-related projects.
Recent amendments to the Brisbane Olympic and Paralympic Games Arrangements Act 2021 (BOPGA Act), introduced through the so-called “Games laws”, establish an alternative pathway for cultural heritage approvals for a limited class of Brisbane 2032 infrastructure.
This article outlines what is changing, which projects are affected, and what this means for proponents, project teams and heritage practitioners.
A new approvals regime for Brisbane 2032 venues and transport infrastructure
The Planning (Social Impact and Community Benefit) and Other Legislation Amendment Act 2025 amends the BOPGA Act to create a tailored approvals framework for certain Brisbane 2032 venues, villages and transport infrastructure, referred to as “authority venues” and project areas.
For these defined Games projects, cultural heritage is managed through a Games-specific process, rather than relying solely on the usual interaction between:
- the Planning Act 2016
- the Queensland Heritage Act 1992
- the Aboriginal Cultural Heritage Act 2003, and
- other relevant State and local laws
Under the Games laws, approvals are centralised within Games delivery entities, including the Games Independent Infrastructure and Coordination Authority (GIICA), and aligned to the strict timeframes required for Games delivery.
How the Games-specific cultural heritage process works
A key feature of the Games laws is the introduction of a formal “cultural heritage notice”.
Once a cultural heritage notice is given for a qualifying Brisbane 2032 project:
- the project transitions into the BOPGA Act approval pathway
- cultural heritage matters are assessed under the Games-specific regime
- decisions are made by designated Games authorities rather than through standard approval pathways
This process is designed to streamline approvals for Games infrastructure, while still requiring heritage considerations to be addressed.
What the Brisbane 2032 Games laws do – and do not – apply to
It is critical to understand that this regime is narrowly targeted.
The Games-specific cultural heritage framework applies only to projects that are:
- expressly identified as Brisbane 2032 authority venues, villages or Games transport infrastructure, and
- regulated under the BOPGA Act
For these projects, compliance with the Games laws can, in certain circumstances, authorise works despite potential inconsistencies with other legislation, provided all Games-specific requirements are met.
However, most projects in Queensland are not affected.
For non-Games projects – including the majority of council works, private developments and regional infrastructure – existing heritage frameworks continue to apply in full, including:
- the Aboriginal Cultural Heritage Act 2003, including Duty of Care and Cultural Heritage Management Plan (CHMP) requirements
- the Queensland Heritage Act 1992
- local planning-scheme heritage overlays and local heritage registers
Practical implications for project teams and proponents
For organisations involved in infrastructure delivery, the key questions are:
- Is the project a Brisbane 2032 authority venue, village or Games transport project?
- If not, standard cultural heritage obligations apply.
- If it is a Games project, which provisions of the BOPGA Act apply?
- This includes understanding the role of the cultural heritage notice, decision-makers, and project-specific timeframes.
Early identification of the correct approvals regime is critical to avoiding delays, compliance risks and stakeholder issues.
How Redleaf is supporting Brisbane 2032 cultural heritage compliance
Redleaf is closely monitoring the evolution of the Brisbane 2032 Games laws and approvals framework.
Where clients become involved in Games-related infrastructure, we can:
- determine whether the Games-specific or standard heritage regime applies
- design heritage methodologies that meet BOPGA Act requirements
- support robust engagement with Traditional Owners and key stakeholders, even within accelerated delivery timeframes
If you would like advice on how the Brisbane 2032 Games laws affect your project, please contact our team.
Other Redleaf Group new articles you might enjoy

Queensland Nature Conservation Act Reforms: What They Mean for Development, Landholders and Industry
Queensland has introduced important reforms to the Nature Conservation Act 1992 (NCA), strengthening how the State manages protected species, wildlife habitat and conservation areas — while improving clarity and consistency around environmental approvals. The updates are designed to ensure responsible development in Queensland with clearer guidance for proponents, landholders, developers and industry. Importantly, the reforms do not reduce environmental protections. Instead, they focus on improving approval pathways, aligning legislation and reinforcing biodiversity safeguards. If you are planning works that may interact with native vegetation, threatened species or protected areas, understanding the updated framework is essential. What Has Changed Under the Nature Conservation Act? The reforms centre on four key objectives: Clearer environmental approval pathways Improved alignment with the Environmental Protection Act 1994 (EP Act) Stronger risk-based decision-making Ongoing protection of biodiversity and threatened flora and fauna Together, these changes aim to reduce uncertainty while maintaining robust environmental standards. Clearer Approvals and Responsibilities for Proponents The reforms provide greater clarity around when approvals are required under the Nature Conservation Act — particularly where projects may: Disturb wildlife habitat Involve clearing in areas supporting protected species Occur within or near protected areas and reserves Updated definitions and guidance are intended to reduce ambiguity and help proponents identify approval requirements earlier in the planning process. Early certainty can significantly reduce redesign, delays and compliance risk. For developers and landholders, this means improved visibility around environmental obligations before construction or operational works commence. Better Alignment with the Environmental Protection Act 1994 A key outcome of the reforms is stronger integration between the Nature Conservation Act and the Environmental Protection Act 1994, as well as related regulatory frameworks. This improved alignment is expected to reduce: Duplicated environmental assessments Conflicting approval conditions Delays caused by disconnected regulatory processes In practical terms, projects that proactively identify environmental risks should benefit from more coordinated and streamlined approvals across State legislation. Continued Strong Protection for Biodiversity in Queensland While the framework improves efficiency, it reinforces Queensland’s commitment to: Protecting threatened species and ecological communities Retaining important habitat values Avoiding, minimising and mitigating environmental impacts Projects with higher environmental risk will continue to undergo rigorous assessment and compliance monitoring. Risk-based decision-making ensures that regulatory scrutiny is proportionate to potential environmental impacts. What Do the NCA Reforms Mean for Your Project? Depending on your activities, the updated Nature Conservation Act framework may influence: Threatened species survey requirements Conditions applied to development approvals Habitat protection, environmental offsets or rehabilitation obligations Timeframes and supporting documentation requirements For many proponents, obtaining early ecological and regulatory advice will become even more important. Identifying environmental risks upfront can help avoid project delays, unexpected conditions and unnecessary costs. How Redleaf Group Supports Clients Under the Revised Nature Conservation Act Redleaf Group works with government, developers, infrastructure providers, industry and landholders across Queensland to help projects proceed confidently and responsibly under environmental legislation. Our services include: Strategic advice on environmental approval pathways Nature Conservation Act compliance and project strategy Threatened species and habitat assessments Preparation of technical reports and supporting documentation Coordination with regulators and key stakeholders Environmental risk management and compliance planning Our approach is practical, collaborative and outcomes-focused — helping clients meet statutory obligations while keeping projects moving efficiently. Need Advice on the Queensland Nature Conservation Act Reforms? If you are planning development, infrastructure, land management or tourism activities that may interact with native vegetation, wildlife habitat or protected areas, our team can provide tailored guidance on: Approval requirements Environmental risks Next steps under the revised framework Get in touch with Redleaf Group

We are excited to announce the launch of redleafgroupheritage.au , showcasing our expanded Heritage Team and our full range of Cultural Heritage, Built Heritage, Native Title, and Training services. On the new site you’ll find: Heritage service overview Profiles of our heritage specialists Project examples and tailored solutions Cultural awareness and heritage training opportunities We welcome your feedback and invite you to explore the new site. Contact: heritage@redleafgroup.au